The first of 3 replacement high efficiency International class boiler feed pumps is being installed by Weir Engineering Services
Ltd at Aberthaw power station near Cardiff South Wales. All work installing the first unit is planned to be complete during
a 48 day programme. A second pump is to be installed between June and July this year with the 3rd unit following on in April
2008. WES are not only responsible for the pump installation but for the modifications to the pipework and civil work as well.
The new pumps were ordered by WES from the Pumps division. The existing units supplied by The Harland Engineering
Company in 1964 are being removed but the existing gearboxes and booster pumps retained for use with the new equipment.
“Being a retrofit installation rather than one on a green field site has called for a number of innovative modifications
to the design of the pumps and associated equipment” said project manager Andy Wagstaff. “Communications and idea exchanges
between the 2 companies have worked well and the project should be completed on schedule”